EXAM QUESTIONS WITH ANSWERS 2024.
"Implementation of TPM Project Flowchart - CORRECT ANSWER Review client RFP
Perform Site Survey
Organize and Submit Bid Questions
Organize and Submit Final Proposal
Client Awards Contract NTP
Contractor Mobilizes
Project Implementation"
"Project - CORRECT ANSWER Temporary endevour that has a definite beginning and end,
whose end result is the delivery of a product or service. Projects are governed by limits
(constraints)."
"Project Constraints - CORRECT ANSWER Time, Cost, Quality, Resources, Risks, Safety,
Technology, Stakeholders, Environment"
"Project Stakeholders - CORRECT ANSWER Sponsor
Portfolio Manager
Client
Sellers
Business Partner
Operations Manager
Functional Manager
Project Manager
Program Manager"
"Project Team Members - CORRECT ANSWER Manufacturer
Engineer
Government / Regulatory
Supplier
Vendor
Admin/ Clerical
Supervisor
Other Trades
Consultant
Coworker
Customer"
2
,"PM Tools - CORRECT ANSWER Program Evaluation Review Technique (PERT)
Gantt - Schedule of activity, bar chart
Critical Path Management
Earned Value Management"
"TPM Steps - CORRECT ANSWER Developing a Plan
Implementing the Plan
Managing/ Tracking the Plan
Closeout the Project"
"TPM Knowledge Areas - CORRECT ANSWER Integration
Scope
Time
Cost
Quality
Human Resources
Communications
Risks
Procurement
Stakeholders"
"Time Management - CORRECT ANSWER Time estimate and schedules
Integration of time schedules from various subteams and calculation of the critical path of
events on the project"
"Cost Management - CORRECT ANSWER Cost estimate and project budget"
"Quality Management - CORRECT ANSWER Detailed review of the design documentation
throughout the project
If ICT completes build, include test results and workmanship
Client value Items"
"Communications Management - CORRECT ANSWER Scheduled meetings and the use of
electronic media
War room - to post schedule and project results on a whiteboard"
2
,"Risk Management - CORRECT ANSWER Injury
Professional damage
Scheduling conflicts
Errors & omissions
Cost risks"
"When should the risk management plan be completed? - CORRECT ANSWER Before a
company submits a proposal"
"Stakeholder Management - CORRECT ANSWER Identify all internal/ external stakeholders"
"Whose job is it to integrate and mitigate the influence and interests of each stakeholder -
CORRECT ANSWER Project Manager"
"Procurement Management - CORRECT ANSWER Procurement of resources outside of the
team, (materials & subcontractors)"
"Client Needs Assessment - CORRECT ANSWER Starts with a meeting with the client to
evaluate their needs"
"ICT Professional must understand: - CORRECT ANSWER Industry, Business, Technology and
Strategic plans"
"ICT Professional should understand: - CORRECT ANSWER Strengths/ Weaknesses
Vertical Market
Unique Requirements"
"Lessons Learned Questions - CORRECT ANSWER What went right/ wrong
What produced best results
What processes can be improved
Did we learn anything"
"Corrective Action Plan - CORRECT ANSWER Should be developed for the purpose of
continuous quality"
"Request for Proposal (RFP) - CORRECT ANSWER Invitation for a contractor to submit
proposal for a service"
2
, "What dictates scope but leaves the decisions to the firm? - CORRECT ANSWER RFP"
"It is advisable for the project manager to send the 90% draft of the RFP to the: - CORRECT
ANSWER Project Manager's Legal Team"
"Violating the Code of Silence: - CORRECT ANSWER will automatically disqualify the
proposal and the company could be further penalized in future RFP submittals"
"Design Team Members - CORRECT ANSWER Owner
Architect
Professional Engineer
Consultant"
"Owner - CORRECT ANSWER Defines requirements, provides approval @ each design
phase"
"Architect - CORRECT ANSWER Lead design professional, hired by the owner"
"Who usually hires professional engineers and consultants? - CORRECT ANSWER Architect"
"Construction Manager - CORRECT ANSWER Hired by Owner to assist in the management of
a bid"
"Construction Managers can also be - CORRECT ANSWER General Contractors"
"CMAR - CORRECT ANSWER CM but acts as the consultant to the owner, or as GC during
construction
Usually the low bidder"
"General Contractor - CORRECT ANSWER Hired by owner to complete work"
"Contractor/ Subcontractor - CORRECT ANSWER Hired by owner or general contractor to
complete a portion of work"
"Design Phases - CORRECT ANSWER Schematic Design
Design Development
2