. All of the following are included in an Agile project charter, except for which one? a) Detailed project scope b) Expected ROI c) Signature and date d) Project goals and objectives: a) Detailed project scope 2. Agile team members have identified a risk in a project and are not able to resolve it due to lack of expertise. You, as a Agile project manager, decided to contract with a third party for resolving the risk. Which of the following risk response strategies have you applied? a) Accept b) Avoid c) Transfer d) Mitigate: c) Transfer 3. When the customer is thinking and explaining something one way and the team takes it in a different way. This is referred to as which of the following? a) The gulf of understanding b) The gulf of misunderstanding c) The gulf of Agile d) The gulf of evaluation : a) The gulf of understanding 4. An Agile team working together on a project are sitting in a big meeting room. In the room, John was discussing with Kim about a security loophole while implementing the code design for a module. In between, Harry, who was listening to their discussion gets an idea on the improvement of current code design and notes it down for further design discussion meeting with architects. He asks John and Kim to park this code implementation for a while and requests them to continue code development of the remaining module. According to the given scenario, this is referred to as which of the following? a) Osmotic communication b) Emotional intelligence c) Nonverbal communication d) Mirroring: b) Emotional intelligence 5. As an Agile project manager, you want to perform a review of your project from several different characteristics. You would like to review what worked on the project and what needed improvement. Which of the following will you use to accomplish the task? a) Kano analysis

Show more Read less
Institution
Module











Whoops! We can’t load your doc right now. Try again or contact support.

Written for

Institution
Module

Document information

Uploaded on
August 19, 2024
Number of pages
38
Written in
2024/2025
Type
Exam (elaborations)
Contains
Questions & answers

Subjects

Content preview

CMGT 410

CMGT 410 - Wk 5 - Apply: Post-Test
All of the following are included in an Agile project charter, except for which one?
a. Detailed project scope
b. Expected ROI
c. Signature and date
d. Project goals and objectives: correct answer- a) Detailed project scope

Agile team members have identified a risk in a project and are not able to resolve it due to lack of
expertise. You, as a Agile project manager, decided to contract with a third party for resolving the risk.
Which of the following risk response strategies have you applied?
a. Accept
b. Avoid
c. Transfer
d. Mitigate: correct answer-c) Transfer

When the customer is thinking and explaining something one way and the team takes it in a different
way. This is referred to as which of the following?
a. The gulf of understanding
b. The gulf of misunderstanding
c. The gulf of Agile
d. The gulf of evaluation: correct answer-a) The gulf of understanding

An Agile team working together on a project are sitting in a big meeting room. In the room, John was
discussing with Kim about a security loophole while implementing the code design for a module. In
between, Harry, who was listening to their discussion gets an idea on the improvement of current code
design and notes it down for further design discussion meeting with architects. He asks John and Kim to
park this code implementation for a while and requests them to continue code development of the
remaining module.
According to the given scenario, this is referred to as which of the following?
a. Osmotic communication
b. Emotional intelligence
CMGT 410

,CMGT 410
c. Nonverbal communication
d. Mirroring: correct answer- b) Emotional intelligence


As an Agile project manager, you want to perform a review of your project from several different
characteristics. You would like to review what worked on the project and what needed improvement.
Which of the following will you use to accomplish the task?
a. Kano analysis
b. MoSCoW
c. Shu Ha Ri
d. SWOT analysis: d) SWOT analysis

Using the following values: earned value = 8,000 planned value = 4,000, actual cost = 3,000, calculate
CV (cost variance).
a. 5,000
b. 4,000
c. 1,000
d. 2,000: a) 5,000

Which of the following is a performance measure, used for evaluating gain or loss generated on an
investment relative to the amount of money invested?
a. IRR
b. INVEST
c. ROI
d. NPV: c) ROI

All of the following are examples of special causes, except for which one?
a. Machine malfunctioning
b. Measurement errors
c. Faulty controllers
d. Computer crashing: b) Measurement errors
CMGT 410

,CMGT 410

In a planning poker session, the cards used are presented with which of the following series for assessing
story points?
a. Arithmetic progression
b. Fibonacci
c. Even
d. Odd: b) Fibonacci

A technique in which multiple team members focus collectively on resolving a specific impediment is
referred to as:
a. Tailoring
b. Grooming
c. Swarming
d. Refactoring: c) Swarming

What is the primary purpose of the retrospective meeting?
a. Discuss what went well, what didn't got so well, and what improvements could be made
immediately in the next iteration.
b. Identify what was learned during the project/program.
c. Demonstrate the completed work to the customer for gaining their feedback and for encouraging
collaboration
d. Discuss and review team practices openly and assess how the team is working together.: a) Discus
what went well, what didn't got so well, and what improvements could be made immediately in the
next iteration.

According to the Agile Manifesto, which of the following is an accurate practice?
a. Contract Negotiation over Customer Collaboration
b. Comprehensive Documentation over Working Software
c. Individuals and Interactions over Processes and Tools
d. Following a Plan over Responding to Change: c) Individuals and Interactions over Processes and
Tools

CMGT 410

, CMGT 410

The Shu Ha Ri model depicts the maturity of learning and application in a team environment. What is the
meaning of the word Sha Ha Ri?
a. Leave, be the rule; learn, follow the rule, detach, break the rule
b. Detach, break the rule; leave, be the rule; learn, follow the rule
c. Learn, follow the rule; detach, break the rule; leave, be the rule
d. Detach, break the rule; separate, be the rule; learn, follow the rule: c) Learn, follow the rule;
detach, break the rule; leave, be the rule

A planning is done at three distinct horizons using which of the following?
a. Wireframe
b. Prototyping
c. Progressive elaboration
d. Kano analysis: c) Progressive elaboration

As an Agile project manager, you are planning a seating arrangement for your project team. You want
that the team sits together in the work area and sees each other. What is the purpose of this arrangement?
Helping the product owner to attend the daily stand-ups
Making the optimum use of available space
Helping a team to see what the other person is doing
Helping in osmotic communication: d) Helping in osmotic communication

You ask the customer to give out fake amount to individual business features to better understand the
project's goal. This is referred to as which of the following?
a. Dot voting
b. Monopoly money
c. MoSCoW
d. 100-point method: b) Monopoly money

In a discussion between two Agile team members, one of the team mem- bers is showing positive
gestures, nodding his head, and asking questions. This is an example of which of the following?
a. Emotional intelligence

CMGT 410

Get to know the seller

Seller avatar
Reputation scores are based on the amount of documents a seller has sold for a fee and the reviews they have received for those documents. There are three levels: Bronze, Silver and Gold. The better the reputation, the more your can rely on the quality of the sellers work.
jacksonruth University Of California - Berkeley
Follow You need to be logged in order to follow users or courses
Sold
38
Member since
1 year
Number of followers
6
Documents
495
Last sold
1 month ago
TUTOR AND MENTOR

I have done papers of various topics and complexities. I am punctual and always submit work on-deadline. I write engaging and informative content on all subjects. Send me your research papers, case studies, psychology papers, etc, and I’ll do them to the best of my abilities. Writing is my passion when it comes to academic work. I’ve got a good sense of structure and enjoy finding interesting ways to deliver information in any given paper. I love impressing clients with my work, and I am very punctual about deadlines. Send me your assignment and I’ll take it to the next level. I strive for my content to be of the highest quality. Your wishes come first— send me your requirements and I’ll make a piece of work with fresh ideas, consistent structure, and following the academic formatting rules. For every student you refer to me with an order that is completed and paid transparently, I will do one assignment for you, free of charge!!!!!!!!!!!!

Read more Read less
3.7

9 reviews

5
4
4
0
3
4
2
0
1
1

Recently viewed by you

Why students choose Stuvia

Created by fellow students, verified by reviews

Quality you can trust: written by students who passed their exams and reviewed by others who've used these revision notes.

Didn't get what you expected? Choose another document

No problem! You can straightaway pick a different document that better suits what you're after.

Pay as you like, start learning straight away

No subscription, no commitments. Pay the way you're used to via credit card and download your PDF document instantly.

Student with book image

“Bought, downloaded, and smashed it. It really can be that simple.”

Alisha Student

Frequently asked questions