QuizDumps provides the best Oracle 1Z0-1057-20 dumps with 100% real 1Z0-1057-20 exam questions for the preparation of the 1Z0-1057-20 exam. These 1Z0-1057-20 exam dumps are helpful to pass the Oracle Project Portfolio Management Cloud 2020 Implementation Essentials Exam in the very first attempt. D...
Thank You For Downloading 1Z0-1057-20 Exam PDF Demo
QuizDumps helps you to prepare Oracle Industries exam. Get most Up-to-Date Oracle
1Z0-1057-20 exam Questions and Answers and pass the 1Z0-1057-20 exam in the first
attempt.
Get Full 1Z0-1057-20 Exam PDF Here
https://quizdumps.com/exam/1z0-1057-20-dumps/
A consulting services company is currently working on a business transformation project for your client,
which spans multiple years. At the first period close, the consulting services company has recognized
revenue and the accounting entry created is:
Dr Unbilled Receivables 40,000
Cr Revenue 40,000
At the end of the period, the client is sent an associated bill. What would be the corresponding invoice
accounting entry? (Choose the best answer.)
A. Dr Unearned Revenue 40,000Cr Accounts Receivables 40,000
B. Dr Accounts Receivables 40,000Cr Unbilled Receivables 40,000
C. Dr Accounts Receivables 40,000Cr Revenue 40,000
D. Dr Unearned Revenue 40,000Cr Revenue 40,000
Answer: B
Question: 2
You want to export your project plan to Oracle Project Financial Management Cloud after initial
scheduling is complete in Microsoft Projects. Identify three conditions that must be met for exporting
milestone tasks. (Choose three.)
A. only one labor resource assignment with 100 effort
B. lowest-level tasks set up with non-zero duration
C. lowest-level tasks set up with zero duration
D. only one labor resource assignment with 0 effort
E. percent work complete values of 0 or 100 percent
Answer: C, D, E
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapex/define-project-
management-configuration.html#OAPEX1357147
Topic - Microsoft Project Prevalidation: Explained
The following table describes Prevalidation rules for tasks and resource assignments.
Level Rule
Lowest-level One labor and multiple expense resources are allowed for a lowest-level task.
,Questions & Answers PDF Page 3
tasks Remove other resources.
Summary Only one labor resource with zero allocation is allowed for a summary task. Remove
tasks all other resources.
Milestone No subtasks are allowed under milestone tasks. Milestones must be lowest-level
tasks tasks.
Milestone Milestone tasks must have zero duration.
tasks
Milestone Only one labor resource, with zero effort, is allowed for a milestone task. Remove all
tasks other resources.
When exporting milestone tasks, ensure that the tasks:
Are lowest-levels task with zero duration, that is, the same start and finish dates.
Have only one labor resource assignment with zero effort.
Have percent work complete values of 0 or 100 percent. Any other values are set to zero before export.
Question: 3
Your customer wants to automatically allocate unassigned asset lines and common costs across multiple
assets based on the construction-in-process cost of each asset. Identify the asset allocation method that
you must use as the default method while configuring project types to meet this requirement. (Choose
the best answer.)
A. Standard Unit Cost
B. Actual Unit
C. Current Cost
D. Estimated Cost
E. Spread Evenly
Answer: C
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-management/19a/oapfm/project-
foundation-configuration-manage-project-types.html#OAPFM220111
Topic – Asset Cost Allocation Methods: Explained
The asset cost allocation method determines how indirect or common costs incurred on a project are
allocated to multiple assets.
You can specify an asset cost allocation method to enable Oracle Fusion Project Costing to automatically
allocate unassigned asset lines and common costs across multiple assets. Unassigned asset lines typically
occur when more than one asset is assigned to an asset grouping level.
Projects and project templates inherit a default asset cost allocation method from the associated project
type. You can override the default at the project level. If you use capital events to allocate costs, then
you can also override the asset cost allocation method at the event level.
The following table describes the available asset cost allocation methods.
Method Basis of Cost Allocation
Actual Units Number of units defined for each asset
,Questions & Answers PDF Page 4
Current Cost Construction-in-process (CIP) cost of each asset
Estimated Cost Estimated cost of each asset
Standard Unit Combination of the standard unit cost and the number of units
Cost defined for each asset
Spread Evenly Equal allocation of cost to each asset
Question: 4
Your customer wants to calculate Estimate to Complete (ETC) as the difference between Current Planned
Cost and Actual Cost. In Progress Settings, which option would you use in conjunction with the ETC
method to meet this requirement? (Choose the best answer.)
A. Effort
B. Cost
C. Manual Entry
D. Remaining Plan
Answer: B
Reference https://ppm-
help.saas.hpe.com/en/9.42/Help/Content/UG/PjMUG/view_pj_cost_data_costtab.htm
Below is an example of the Financial Summary view on the Cost tab of the Project Overview page.
, Questions & Answers PDF Page 5
Question: 5
Which five steps are required for the File-Based Data Import Integration option?
A. Run Process to transfer data to interface tables.
B. Install an Excel add-in.
C. Upload the file to the server.
D. Download an Excel template.
E. Populate the spreadsheet with data and generate a CSV file.
F. Import data into various applications.
Answer: A B C D E
Ref: https://docs.oracle.com/en/cloud/saas/project-portfolio-
management/19b/oefpp/overview.html#External_Data_Integration_Services_for_Oracle_Cloud_Overvi
ew
The benefits of buying summaries with Stuvia:
Guaranteed quality through customer reviews
Stuvia customers have reviewed more than 700,000 summaries. This how you know that you are buying the best documents.
Quick and easy check-out
You can quickly pay through credit card for the summaries. There is no membership needed.
Focus on what matters
Your fellow students write the study notes themselves, which is why the documents are always reliable and up-to-date. This ensures you quickly get to the core!
Frequently asked questions
What do I get when I buy this document?
You get a PDF, available immediately after your purchase. The purchased document is accessible anytime, anywhere and indefinitely through your profile.
Satisfaction guarantee: how does it work?
Our satisfaction guarantee ensures that you always find a study document that suits you well. You fill out a form, and our customer service team takes care of the rest.
Who am I buying these notes from?
Stuvia is a marketplace, so you are not buying this document from us, but from seller melaniecampbell. Stuvia facilitates payment to the seller.
Will I be stuck with a subscription?
No, you only buy these notes for £0.00. You're not tied to anything after your purchase.