1. Bridge cranes with rated capacities of Category 2
20,000 lbs. or greater are classified as
______ cranes
2. The expiration date that is of particular im- The certification expiration date of the crane
portance to crane operators is
3. Who is primarily responsible for evaluating crane operator
a Crane Operators physical and emotional
fitness
4. A monorail hoist with less than 20,000 lbs. Category 3
capacity is a ________________ crane.
5. Components that control, restrain, or posi- load controlling parts
tion the load, and upon failure would cause
dropping, shifting or uncontrolled move-
ment of the loads are ____________.
6. All of the following require a license to op- Non-cab operated category 3-bridge crane
erate EXCEPT a:
7. What is two-blocking and why is two-block- Two-blocking occurs when the hook block
ing dangerous? comes in contact with the upper sheave
block during hoisting of the hook. It is dan-
gerous because it could result in damage
to the crane, parting of the hoist lines, and
dropping the load.
8. The formula for determining the area of a Base x Height divided by 2
triangular shaped object is:
9. Prior to the first use of the crane each day.
1/9
, CATEGORY 3 NON-CAB OPERATED TEST
Study online at https://quizlet.com/_75uqmx
When are operators required to perform a
pre-use check of the crane?
10. Regardless of the method of communi- clear
cation used all crane signals must be
____________________.
11. Synthetic web slings should NOT be used True
in areas where temperatures exceed 194
degrees Fahrenheit.
12. If an object is 6 feet long, 5 feet wide, and 4 120 cubic feet
feet high, what is the volume of the object?
13. Is it necessary for the operator to see the Not if there is a designated signal person
load or work area? who is in control of the lift and is in view
of the operator, or if the signal giver is in
constant radio contact with the operator.
14. What is "inching"? Performing a motion very slowly, a little at a
time
15. The majority of crane accidents are attrib- Personnel error
uted to which of the following?
16. Crane operators at naval activities may be Be familiarized by a qualified person before
required to operate various types of cranes operating the crane for the first time
for which they hold a license. Which of the
following can best assure operator profi-
ciency and safety?
17. Which of the following is NOT an accept- Signal Flags
able method of communication between
the signal person and the crane operator?
2/9
CATEGORY 3 NON-CAB OPERATED TEST
ANSWERS || LATEST EXAM 2025/2026||EXAM GRADED A+
Study online at https://quizlet.com/_75uqmx
1. Bridge cranes with rated capacities of Category 2
20,000 lbs. or greater are classified as
______ cranes
2. The expiration date that is of particular im- The certification expiration date of the crane
portance to crane operators is
3. Who is primarily responsible for evaluating crane operator
a Crane Operators physical and emotional
fitness
4. A monorail hoist with less than 20,000 lbs. Category 3
capacity is a ________________ crane.
5. Components that control, restrain, or posi- load controlling parts
tion the load, and upon failure would cause
dropping, shifting or uncontrolled move-
ment of the loads are ____________.
6. All of the following require a license to op- Non-cab operated category 3-bridge crane
erate EXCEPT a:
7. What is two-blocking and why is two-block- Two-blocking occurs when the hook block
ing dangerous? comes in contact with the upper sheave
block during hoisting of the hook. It is dan-
gerous because it could result in damage
to the crane, parting of the hoist lines, and
dropping the load.
8. The formula for determining the area of a Base x Height divided by 2
triangular shaped object is:
9. Prior to the first use of the crane each day.
1/9
, CATEGORY 3 NON-CAB OPERATED TEST
Study online at https://quizlet.com/_75uqmx
When are operators required to perform a
pre-use check of the crane?
10. Regardless of the method of communi- clear
cation used all crane signals must be
____________________.
11. Synthetic web slings should NOT be used True
in areas where temperatures exceed 194
degrees Fahrenheit.
12. If an object is 6 feet long, 5 feet wide, and 4 120 cubic feet
feet high, what is the volume of the object?
13. Is it necessary for the operator to see the Not if there is a designated signal person
load or work area? who is in control of the lift and is in view
of the operator, or if the signal giver is in
constant radio contact with the operator.
14. What is "inching"? Performing a motion very slowly, a little at a
time
15. The majority of crane accidents are attrib- Personnel error
uted to which of the following?
16. Crane operators at naval activities may be Be familiarized by a qualified person before
required to operate various types of cranes operating the crane for the first time
for which they hold a license. Which of the
following can best assure operator profi-
ciency and safety?
17. Which of the following is NOT an accept- Signal Flags
able method of communication between
the signal person and the crane operator?
2/9