___ ___ are the amounts needed week by Blank 1: Net
week in the future over and above what Blank 2: Requirements
is currently on hand or committed to
through an order already released and
scheduled.
___ ___ are the total amount required for a
particular item.
At any point in time, an MRP system can inventory records file
reference the ____ for instantaneous parts
availability to help meet gross
requirements.
Available to promise is a powerful tool Coordinating sales and production activities
for what?
Identifies the specific materials used to make each item and the correct
BoM
quantities of each.
EOQ assumes that parts are used ___ continuously
during the period.
, MQM 227 Ch.21 Questions and Answers 100% Correct
An EOQ lot sizing technique will try to Setup
minimize which of the following costs Inventory holding
given a fairly constant demand? Check
all that apply.
Setup
Inventory holding
Marketing
Transportation
EOQ was not designed for a system like MRP has discrete time periods
MRP. Why not?
Examples: piston rings, electrical Make-to-stock
switches. What is the industry type?
Examples: trucks, generators, motors. Assemble-to-order
What is the industry type?
Examples: turbine generators, heavy Engineer-to-order
machine tools. What is the industry type?
, MQM 227 Ch.21 Questions and Answers 100% Correct
The file created by retracing a material peg
requirement upward in the product
structure to identify each parent item
that created the demand is called a ___
record file.
A final assembly is made from standard Assemble-to-order
options that the customer chooses.
Finished goods purchased by individuals Independent demand items
external to the organization are
considered what?
For Ford Motor Company, which of the Cars
following items would appear on its Trucks
master production schedule? Check all Vans
that apply.
Hoses
Engines
Cars
Fan belts
Trucks
Vans
Transmissions