MICHIGAN BUILDERS LICENSE EXAM NEWEST 2026
COMPLETE ALL 230 QUESTIONS AND CORRECT
DETAILED ANSWERS (VERIFIED ANSWERS)
|ALREADY GRADED A+||NEWEST EXAM!!!
The right amount of moisture and limitations with regard to
excessive heat or cold have an impact on which of these
in regards to concrete? - ANSWER-All of these
Flashing is so important in brick masonry because -
ANSWER-moisture is one of the biggest issues in
masonry
Cindy needs to do some repair work to her home before
putting it on the market . She needs mortar to fill in a few
unsightly cracks in brick patio, but is unsure of which type
to get. Given the information provided, which type of these
would be her best option? - ANSWER-Type N
Which of the following applies to unfilled hollow masonry
piers supporting a beam - ANSWER-Unsupported height
cannot exceed 4 times the least dimension
A ________ is a built-out portion of a wall that forms a
bulge. - ANSWER-pilaster
,2|Page
CMUs are often used in all these except - ANSWER-rafter
construction
What is the minimum engagement of wall tie embedment
in solid masonry units - ANSWER-1 1/2"
The temperature of new concrete should not be allowed to
fall below ______ F during the curing period - ANSWER-
50
Michigan Labor Laws require employers to provide
employees under _____ with a 30 minute rest period if
scheduled more than 5 continuous hours - ANSWER-18
Which of the following is not acceptable as proof of a legal
right to work in the U.S.? - ANSWER-Bank or credit card
plus social security card
An occupational injury and illness log must be kept at
every job site for business with more than how many
employees - ANSWER-10
,3|Page
Which of these incidents would NOT need to be reported
within 24 hours? - ANSWER-A crew getting into a car
accident on the way o a site
A Michigan employer is required to provide which of the
following for adult employees - ANSWER-None of these
Businesses with more than 50 full time employees that
don't offer insurance may be subject to what payment? -
ANSWER-The employer shared responsibility payment
Which of these is included in material costs? - ANSWER-
Inspection of materials
Horizontal dimensions on a building plan can be found on
the ________. - ANSWER-Plan View
What is the ratio between the size of the object as drawn
and its actual size called? - ANSWER-Scale
Which type of Plan allows for a house to be sliced
vertically to see information about materials, fastening,
, 4|Page
and support systems, and concealed features? -
ANSWER-Section view
What kind of contaminants are found in traditional building
materials and absent from green building materials? -
ANSWER-Volatile organic compounds
The seal and signature of an architect or professional
engineer is required on all construction documents when
applying for a building permit for any one or two family
dwelling project over _____ square feet - ANSWER-3500
When submitting construction plans tot he local building
department, which of these does not need to be in the
cover sheet? - ANSWER-a scale bar to show the chosen
scale
A description or identification of the materials to be used in
a project will be found in the project _________ -
ANSWER-Specifications
In a construction plan, a section view would be named
with a/an ______ - ANSWER-A