1. Three ways to modify contract documents after execution: 1. Supplemental Agreemen
2. Work order
3. Unilateral Payment
2. Order of document precedence: Special Provision
Technical Special Provision
Plans
Standard plans
Developmental Specifications
Supplemental Specifications
Standard Specifications for Road bridge
3. Contractor's monthly payment is based on?: Monthly progress estimates
4. When is retainage withheld?: 1. Percent of allowable contract used exceeds 75%
AND
Ditterence in percentage of contract time used exceeds the percentage of contract amount earned by m
5. Three ways to modify contract documents: 1. Supplemental Agreement
2. Work order
3 unilateral payment
6. Work orders are funded through:: Initial contingency amount (999-25-XX)
Contingency supplemental agreement (CSA), which can't be issued until at least 50% of initial contingency amount pay
item funds are expended
, 7. What is an unilateral payment?: Disagreement between dept and contractor on terms or contractor
fails to timely execute a WO or SA
8. Liqudated Damages can be refunded on monthly progress estimate?: True
9. Calculate error in plan quantity: