WGU C722 PRACTICE TEST | COMPLETE QUESTIONS & ANSWERS
(100% VERIFIED SOLUTIONS) LATEST UPDATE
A firm begins its strategic business initiative of developing a new business model that will allow
the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm
initiates a business management project.
Which aspect of project management applies to this firm's project? - CORRECT ANSWER -
Interdependent tasks
A firm begins its strategic business initiative of developing a new business model to enhance its
competitiveness.
What can be identified as a strategic business initiative for this firm? - CORRECT ANSWER -
Improvement in product design
A firm begins a strategic business initiative of developing a new business model that will allow
the firm to deliver an efficient, tailored service to its customers.
Which stakeholder would have triggered this strategic business initiative? - CORRECT
ANSWER -Project sponsor
Which group is included in the five process groups? - CORRECT ANSWER -Closing process
group
What does PRINCE2 stand for? - CORRECT ANSWER -PRojects IN a Controlled Environment
Which PMBOK process group is described as the delivery part of project management where the
main activity happens? - CORRECT ANSWER -Executing
, Which advantage does the functional (departmentalized) organizational structure provide for a
firm with multiple projects? - CORRECT ANSWER -Lines of authority are clear.
Which two organizations are examples of organizations with the functional organizational
structure? - CORRECT ANSWER -The U.S. Department of State & The U.S Department of
Energy
An organization expects to use a project management office (PMO) to support multiple projects
that will be implemented within a projectized organizational structure.
Which implied effect is a benefit to this organization? - CORRECT ANSWER -Project team
members gain access to historical data from other projects.
Regardless of the organizational structure used to manage a project, an organization elects to use
a project management office (PMO).
Which benefit will this organization gain? - CORRECT ANSWER -Projects will coordinate
resource usage by monitoring the status of shared resources.
During a certain project phase, specific blueprints are drawn and approved, materials and labor
costs are estimated, prototypes are created, and work activities and tasks are identified. Also,
quality expectations, measurements, and costs are defined.
During which project phase do these activities occur? - CORRECT ANSWER -Planning
Place the project activities in order of occurrence from first (1) to last (5). - CORRECT
ANSWER -Collecting customer requirements 1
Developing the work breakdown structure 2
(100% VERIFIED SOLUTIONS) LATEST UPDATE
A firm begins its strategic business initiative of developing a new business model that will allow
the firm to deliver an efficient, tailored service to its customers. To accomplish this, the firm
initiates a business management project.
Which aspect of project management applies to this firm's project? - CORRECT ANSWER -
Interdependent tasks
A firm begins its strategic business initiative of developing a new business model to enhance its
competitiveness.
What can be identified as a strategic business initiative for this firm? - CORRECT ANSWER -
Improvement in product design
A firm begins a strategic business initiative of developing a new business model that will allow
the firm to deliver an efficient, tailored service to its customers.
Which stakeholder would have triggered this strategic business initiative? - CORRECT
ANSWER -Project sponsor
Which group is included in the five process groups? - CORRECT ANSWER -Closing process
group
What does PRINCE2 stand for? - CORRECT ANSWER -PRojects IN a Controlled Environment
Which PMBOK process group is described as the delivery part of project management where the
main activity happens? - CORRECT ANSWER -Executing
, Which advantage does the functional (departmentalized) organizational structure provide for a
firm with multiple projects? - CORRECT ANSWER -Lines of authority are clear.
Which two organizations are examples of organizations with the functional organizational
structure? - CORRECT ANSWER -The U.S. Department of State & The U.S Department of
Energy
An organization expects to use a project management office (PMO) to support multiple projects
that will be implemented within a projectized organizational structure.
Which implied effect is a benefit to this organization? - CORRECT ANSWER -Project team
members gain access to historical data from other projects.
Regardless of the organizational structure used to manage a project, an organization elects to use
a project management office (PMO).
Which benefit will this organization gain? - CORRECT ANSWER -Projects will coordinate
resource usage by monitoring the status of shared resources.
During a certain project phase, specific blueprints are drawn and approved, materials and labor
costs are estimated, prototypes are created, and work activities and tasks are identified. Also,
quality expectations, measurements, and costs are defined.
During which project phase do these activities occur? - CORRECT ANSWER -Planning
Place the project activities in order of occurrence from first (1) to last (5). - CORRECT
ANSWER -Collecting customer requirements 1
Developing the work breakdown structure 2