What is the maximum amount of time after Substantial Completion of the Work
shall all claims (by Owner and Contractor) regarding the Contract by commenced?
1- Six months
2- One year
3- Ten years
4- Five years - ANSWER-A201: 13.7
Article 13: Miscellaneous Provisions
13.7 Time Limits on Claims
3- Ten years
The ____________ shall secure and pay for necessary approvals, easements,
assessments and changes required for construction
1- Owner
2- Subcontractor
3- Architect
4- Contractor - ANSWER-A201: 2.2.2
Article 2) Owner
pg. 1
,2.2 Information and Services Required of the Owner
1- Owner
The Contractor wishes to make a Claim for an increase in the Contract Sum.
Written notice as provided herein shall be given ______________.
1- Before, after, or during the execution of the Work
2- After proceeding to execute the Work
3- During the execution of the Work
4- Before proceeding to execute the Work - ANSWER-A201: 15.1.4
Article 15) Claims and Disputes
15.1 Claims
15.1.4 Claims for Additional Cost
4- Before proceeding to execute the Work
Who is responsible for purchasing and maintaining insurance that will insure the
Owner against loss of use? (Note that this insurance is OPTIONAL)
1- Contractor
2- Architect
pg. 2
,3- Owner
4- Subcontractor - ANSWER-A201: 11.3.3
Article 11) Insurance and Bonds
11.3 Property Insurance
3- Owner
Who is required to give notices required by codes regarding safety of persons or
their protection from loss?
1- Owner
2- Contractor
3- Architect
4- Inspector - ANSWER-A201: 10.2.2
Article 10) Protection of Persons and Property
10.2 Safety Precautions and Programs
2- Contractor
A201 contains provisions for mediation and arbitration. __________ is not
required under A201 while __________is.
pg. 3
, 1- resolution; mediation
2- arbitration; mediation
3- mediation; arbitration
4- arbitration; resolution - ANSWER-A201: Page 2
Dispute Resolution - Mediation and Arbitration
2- arbitration; mediation
A Construction Change Directive requires agreement between which of the
following?
1- Owner and Contractor
2- Owner, Contractor, and Architect
3- Owner and Architect
4- Architect and Contractor - ANSWER-A201: 7.1.2
Article 7) Changes in the Work
7.1 General
2- Owner, Contractor, and Architect
pg. 4