100% de satisfacción garantizada Inmediatamente disponible después del pago Tanto en línea como en PDF No estas atado a nada 4.2 TrustPilot
logo-home
Examen

Latest FL Contractor’s Exam Test Bank with 400 Real Exam Questions and Correct Answers / FL Contractor’s Manual 400 Latest Correctly Answered Questions

Puntuación
-
Vendido
-
Páginas
73
Grado
A+
Subido en
11-10-2025
Escrito en
2025/2026

Latest FL Contractor’s Exam Test Bank with 400 Real Exam Questions and Correct Answers / FL Contractor’s Manual 400 Latest Correctly Answered Questions

Institución
FL Contractor’s Manual
Grado
FL Contractor’s Manual











Ups! No podemos cargar tu documento ahora. Inténtalo de nuevo o contacta con soporte.

Escuela, estudio y materia

Institución
FL Contractor’s Manual
Grado
FL Contractor’s Manual

Información del documento

Subido en
11 de octubre de 2025
Número de páginas
73
Escrito en
2025/2026
Tipo
Examen
Contiene
Preguntas y respuestas

Temas

  • florida

Vista previa del contenido

Latest FL Contractor’s Exam Test Bank with 400
Real Exam Questions and Correct Answers /
2025-2026 FL Contractor’s Manual 400 Latest
Correctly Answered Questions

According to the Florida Statues, Chapter 489, a contractor was found guilty of
allowing their certificate to be used by uncertified persons with intent to evade the
provisions of Chapter 489.The Construction Industry Licensing Board may revoke
the certificate of the contractor, require financial restitution to a consumer, and
impose an administrative maximum fine of _____________.


a. $5,000
b. $5,000 or assess costs associated with investigation and prosecution
c. $10,000
d. $10,000 or assess costs associated with investigation and prosecution -
ANSWER-d. $10,000 or assess costs associated with investigation and prosecution
489.129(1)


According to "The Florida Worker's Compensation Law," a determination of
benefits will be based on a calculation involving the last __________ weeks of
employment.


A. 3 weeks
B. 10 weeks
C. 13 weeks
D. 52 weeks - ANSWER-C. 13 weeks
440.14


pg. 1

,Your company signed a contract on June1, 2016, which established a project
completion time of eight months with a liquidated damages provision in the
amount of $100 per day for each and every day over the eight month deadline. Due
to an oversight, the owner failed to file a Notice of Commencement until August1,
2016. What is the effective first day that penalties will accrue to the project?


A. March 2, 2016
B. March 1, 2016
C. March 2, 2017
D. April 2, 2017 - ANSWER-C. March 2, 2017
8 months after Feb 1, 2017 plus one day


Your company was involved with a dispute with an owner over a contract to
construct a 14,000 sq. ft. warehouse valued at $1,437,000. The original contract
was signed February 4, 1999, and was brought to substantial completion on
November 15, 1999. The dispute centers on a change order which was approved by
owner and architect on October 21, 1999, but which the owner has refused to pay.
Assuming the facts as stated and no additional information is provided, should
your company prevail, it should be entitled to:


A. The original contract price and the value of the change order plus special
damages, if any.
B. The original contract price and the value of the change order plus liquidated
damages only.
C. The original contract price and the value of the change order plus loss of profits
only.
D. The original contract price and the value of the change order only. - ANSWER-
A. The original contract price and the value of the change order plus special
damages, if any.


pg. 2

,8-13


In order for a contractor to be assured he has the right to inspect and cure an
alleged defect in construction, the contract must contain which of the following
clauses in BOLD FACED TYPE?


A. Ch. 489 Notice of Claim
B. Ch. 455 Notice of Claim
C. Ch. 558 Notice of Claim
D. Ch. 713 Notice of Claim - ANSWER-C. Ch. 558 Notice of Claim
8-17


According to the Florida Contractors Manual, which of the following are not one
of the three essential items of a construction contract?


A. what is to be performed or built
B. when it will be built
C. how much and when payment will be made
D. name of consumer - ANSWER-D. name of consumer
8-6


According to Contractors Manual, which formula is correct? - ANSWER-Assets-
Liabilities = Owner's Equity


According to Florida Contractors Manual, accounts receivable are classified as: -
ANSWER-assets




pg. 3

, According to the AIA documents, if the primary General Contractor defaults and
the Owner files an affidavit to take over the project, how much time do the
subcontractors and material suppliers have to file liens if the Notice to Owner is
filed properly?


a. 45 days
b. 60 days
c. 30 days
d. 90 days - ANSWER-d. 90 days
9-27


An active certified residential contractor is eligible to take the general contactors'
examination if he possesses a minimum of …….years of proven experience in the
classification in which he is certified.


a. 1
b. 2
c. 3
d. 4 - ANSWER-d. 4
489.111


An active certified air-conditioning Class B contractor is eligible to take the air-
conditioning Class A contactors' examination if he possesses a minimum of years
of proven experience in the classification in which he is certified.


a. 1
b. 2
c. 3

pg. 4
$29.99
Accede al documento completo:

100% de satisfacción garantizada
Inmediatamente disponible después del pago
Tanto en línea como en PDF
No estas atado a nada

Conoce al vendedor

Seller avatar
Los indicadores de reputación están sujetos a la cantidad de artículos vendidos por una tarifa y las reseñas que ha recibido por esos documentos. Hay tres niveles: Bronce, Plata y Oro. Cuanto mayor reputación, más podrás confiar en la calidad del trabajo del vendedor.
muriithikelvin Chamberlain College Nursing
Ver perfil
Seguir Necesitas iniciar sesión para seguir a otros usuarios o asignaturas
Vendido
1412
Miembro desde
2 año
Número de seguidores
552
Documentos
2842
Última venta
2 días hace
GOLD-RATED TOP SELLER ON STUVIA – YOUR TRUSTED HUB FOR EXCEPTIONAL STUDY RESOURCES! ACHIEVE MORE WITH EXPERTLY CRAFTED MATERIALS THAT GUARANTEE RESULTS!

Feeling overwhelmed by exams? We’re here to help. Our study materials help you focus, build confidence, and walk into your exams ready. Compiled using real past exams, these resources give you valuable insight into the kinds of questions to expect and how to approach them — helping you maximize your scores and study smarter. Why Choose Us? Gold-rated seller. 1,250+ happy students. Trusted resources for healthcare and certification success. Friendly support whenever you need it.

Lee mas Leer menos
3.9

278 reseñas

5
139
4
55
3
41
2
14
1
29

Recientemente visto por ti

Por qué los estudiantes eligen Stuvia

Creado por compañeros estudiantes, verificado por reseñas

Calidad en la que puedes confiar: escrito por estudiantes que aprobaron y evaluado por otros que han usado estos resúmenes.

¿No estás satisfecho? Elige otro documento

¡No te preocupes! Puedes elegir directamente otro documento que se ajuste mejor a lo que buscas.

Paga como quieras, empieza a estudiar al instante

Sin suscripción, sin compromisos. Paga como estés acostumbrado con tarjeta de crédito y descarga tu documento PDF inmediatamente.

Student with book image

“Comprado, descargado y aprobado. Así de fácil puede ser.”

Alisha Student

Preguntas frecuentes