ARMY EXPLOSIVES SAFETY SITE PLANNING CERTIFICATION EXAM
NEWEST 2025/2026 COMPLETE 100 QUESTIONS AND CORRECT
ANSWERS (VERIFIED ANSWERS) |ALREADY GRADED A+||BRAND
NEW VERSION!!
Which three items are included in the Evaluations section of an ESSP
package? - ANSWER-Electrical installation
Lightning protection information
Glass hazard risk assessment
What part of the ESSP package contains background information, site
location, and reason for the ESSP? - ANSWER-ESSP narrative
Who has ultimate approval authority for an ESSP? - ANSWER-DoD
explosives Safety Board (DDESB)
The purpose of an Expedited Approval Request is to - ANSWER-Justify why
an expedited approval is required
Which four items are required on installation maps? - ANSWER-Installation
boundaries
Roads and railways
, 2|Page
Waterways and ponds
Facilities and associated utilities
Which of these is a site map requirement? - ANSWER-Scale 1 in = 400 ft
Which four items are required parts of the Transmittal Memorandum? -
ANSWER-Applicable explosives safety reference
Site location
Requested approve by date
Point of contact (POC) for the ESSP
Which three mistakes commonly occur when submitting an ESSP? -
ANSWER-submitting a map without an indication of true north
Leaving out the lightning protection system (LPS) drawings
Sending a map with no scale indicated
The purpose of an ESSP is to ensure safety, provide specifications, and -
ANSWER-establish limits
ILD is the minimum distance permitted between - ANSWER-two operating
buildings