Questions and Correct Answers | Latest
Version | Graded A+ | Verified Answers |
Newest Exam
On day two of PI Planning, management presents adjustments based on the
previous day's management review and problem-solving meeting. What is one
possible type of adjustment they could make?
A. Create new User Stories
B. Adjust business priorities
C. Change a team's plan
D. Redefine the length of the PI ---------CORRECT ANSWER-----------------B. Adjust
business priorities
What is the recommended final agenda item of PI Planning?
A. Surfacing the ART risks
B. Taking the PI confidence vote
C. Reviewing the final plan
D. Participating in the planning retrospective ---------CORRECT ANSWER---------------
--D. Participating in the planning retrospective
,What is one of the Product Owner's responsibilities?
A. To manage and prioritize the Team Backlog
B. To facilitate team meetings and drive Agile behavior
C. To foster normalized estimating within a team
D. To foster adoption of Agile technical practices ---------CORRECT ANSWER----------
-------A. To manage and prioritize the Team Backlog
What is one Story component to consider when estimating size?
A. Scope
B. Depth
C. Knowledge
D. Dependency ---------CORRECT ANSWER-----------------C. Knowledge
In the ART Kanban some steps have work in process (WIP) limits. Why is this
necessary?
A. To reduce handoffs and dependencies
B. To ensure large queues are not forming
C. To support multitasking
,D. To enable Continuous Deployment ---------CORRECT ANSWER-----------------B. To
ensure large queues are not forming
What is the primary purpose of the ART Planning Board?
A. To show sizing of the Epics in relation to each other
B. To show dependencies between teams relating to the Feature development
C. To show Feature priority in association with business value
D. To satisfy System Demo expectation by demonstrating incremental delivery ----
-----CORRECT ANSWER-----------------B. To show dependencies between teams
relating to the Feature development
Which of the following is an output of the PI Planning process?
A. PI Objectives
B. PI Goals
C. PI Vision
D. Actual PI Business Value ---------CORRECT ANSWER-----------------A. PI Objectives
What is one of the SAFe Core Values?
A. Built-in quality
, B. Culture
C. Flow
D. Transparency ---------CORRECT ANSWER-----------------D. Transparency
Which statement correctly describes one aspect of the team's commitment at the
end of PI Planning?
A. A team commits to all the Features they put on the ART planning board
B. A team commits only to the PI Objectives with the highest business value
C. A team commits to all the Stories they put on their PI plan
D. A team does not commit to uncommitted objectives ---------CORRECT ANSWER-
----------------D. A team does not commit to uncommitted objectives
What is used to capture the current state of the Portfolio and provide input for
defining the future state?
A. Portfolio Vision
B. Portfolio Kanban
C. Portfolio Canvas
D. Portfolio Backlog ---------CORRECT ANSWER-----------------C. Portfolio Canvas
Which SAFe Lean-Agile Principle includes an emphasis on "deliver early and
often"?