A communication management plan identifies the relevant information that should be
communicated to... - ANS-the project stakeholders
A project can be split into phases in order to... - ANS-facilitate formal go/no-go decision making
during the project
A project issue is... - ANS-a major problem that requires formal escalation
A responsibility of the project manager is... - ANS-to deliver the project objectives to enable
benefits to be realised
A user... - ANS-those intended to receive benefits or operate outputs
A valid KPI could be... - ANS-milestone achievement
How would you best describe project management? - ANS-the application of processes and
methods to achieve the project objectives
How would you define an estimate? - ANS-an approximation of project time and cost targets,
refined throughout the project life cycle
Project change control primarily seeks to ensure - ANS-all variance to the project scope is
evaluated
Project reporting can best be defined as... - ANS-informing stakeholders about the project
Project risk management is best described as... - ANS-minimising threats and maximising
opportunities
Quality is best defined as... - ANS-fitness for purpose of deliverables
Scheduling can best be defined as the process used to determine... - ANS-overall project
duration
The justification for the investment to be made in a project is documented in the... -
ANS-business case
The main outcome of risk identification, in a risk management process, is to... - ANS-identify and
describe all risk that might occur on the project