100% tevredenheidsgarantie Direct beschikbaar na je betaling Lees online óf als PDF Geen vaste maandelijkse kosten 4.2 TrustPilot
logo-home
Tentamen (uitwerkingen)

VA CONTRACTORS: VA ADVANCED (CLASS A) Exam 2025 UPDATE/PRACTICE QUESTIONS AND CORRECT VERIFIED ANSWERS(complete solutions)ASSURED SUCCESS/GRADED A+!!!

Beoordeling
-
Verkocht
-
Pagina's
6
Cijfer
A+
Geüpload op
26-05-2025
Geschreven in
2024/2025

VA CONTRACTORS: VA ADVANCED (CLASS A) Exam 2025 UPDATE/PRACTICE QUESTIONS AND CORRECT VERIFIED ANSWERS(complete solutions)ASSURED SUCCESS/GRADED A+!!!

Instelling
VA CONTRACTORS: VA ADVANCED
Vak
VA CONTRACTORS: VA ADVANCED









Oeps! We kunnen je document nu niet laden. Probeer het nog eens of neem contact op met support.

Geschreven voor

Instelling
VA CONTRACTORS: VA ADVANCED
Vak
VA CONTRACTORS: VA ADVANCED

Documentinformatie

Geüpload op
26 mei 2025
Aantal pagina's
6
Geschreven in
2024/2025
Type
Tentamen (uitwerkingen)
Bevat
Vragen en antwoorden

Onderwerpen

Voorbeeld van de inhoud

VA CONTRACTORS: VA ADVANCED (CLASS A) Exam 2025
UPDATE/PRACTICE QUESTIONS AND CORRECT VERIFIED
ANSWERS(complete solutions)ASSURED SUCCESS/GRADED A+!!!




What is the total project overhead for a project that lasts 3 months and has the
following costs? Labor is $4,000; materials are $9,500; equipment rentals are
$1,200; superintendent's annual salary is $36,000; office rent is $800 per month;
and office utilities are $375 per month. - CORRECT ANSWER-Less than $12,000



For 1 month a company bills out $38,000 in completed work, and receives
$22,000 in payments plus $8,000 from the previous month's billings. They pay
their total bill of $26,000 to supply houses for this month's purchases, and
another $5,000 to supply houses for last month's purchases. Using a cash
accounting method and NOT considering any other revenue or expenses, what is
the company's net income for the month? - CORRECT ANSWER-Loss of $1,000



The owner requests for change which will cost the contractor $15,000 in labor
and materials and $2,250 in overhead costs. With the change, the contractor
would be relieved of $18,000 in labor and materials costs, and $2,400 in overhead
costs from the original contract. The original bid included profit of 20% of all
costs. The contractor wants to make a profit of 20% of all costs on the changes.
The adjusted contract price for the change order should be... - CORRECT
ANSWER-A decrease of $3,780

, A lump sum contract on a project has a total contract price of $160,000.
Retainage has been held back at 10%. The contractor has received progress
payments for 75% of the project. The contractor submits a request for final
payment for the new completed project. The final payment amount should be
for... - CORRECT ANSWER-More than $50,000



What is the total value of current assets for an accrual basis company that has the
following? Checking account cash balance is $4,800; materials inventory for work-
in-progress is $4,200; a pick-up truck that cost $12,460- paid for with $2,460 in
cash and a note for $10,000- and is used 100% in the business; accounts
receivable is $5,700; suppliers' accounts payable is $6,300; other accounts
payable is $2,200; and quarterly income tax payment due is $1,180... - CORRECT
ANSWER-Between $12,000 and $16,000



Which of the following would typically be covered by a contractor's
comprehensive general liability insurance policy? - CORRECT ANSWER-Damage
to adjoining property from a crane accident



What is the total gross compensation and employment status for a carpenter,
given the following information? A contractor hires a carpenter to do the finish
work for a 10-home project. The carpenter is to be paid $16 per hour. The
contractor provides all materials and equipment, such as a table saw. The
carpenter provides all of his own hand tools. The contractor and the carpenter
agree that all of the homes are to be completed within 60 8-hour working days,
without overtime. The contractor provides the carpenter with a schedule of the
order in which homes are to be worked on. The contractor provides a helper to
assist the carpenter. The contractor sets the work schedule each day. The
carpenter spends 600 hours to complete this project, including 120 hours of

Maak kennis met de verkoper

Seller avatar
De reputatie van een verkoper is gebaseerd op het aantal documenten dat iemand tegen betaling verkocht heeft en de beoordelingen die voor die items ontvangen zijn. Er zijn drie niveau’s te onderscheiden: brons, zilver en goud. Hoe beter de reputatie, hoe meer de kwaliteit van zijn of haar werk te vertrouwen is.
trustednurse NURSING
Bekijk profiel
Volgen Je moet ingelogd zijn om studenten of vakken te kunnen volgen
Verkocht
863
Lid sinds
2 jaar
Aantal volgers
401
Documenten
6274
Laatst verkocht
8 uur geleden

On this platform, you will discover a variety of meticulously crafted study materials, including detailed documents, comprehensive bundles, and expertly designed flashcards provided by the seller, Trustednurse. These resources are thoughtfully prepared to support your learning journey and make your studies and exam preparations smooth and effective. I am here to offer any assistance or answer any questions you may have regarding your academic needs. Please don’t hesitate to reach out for guidance or support—I am more than happy to help you achieve success in your courses and exams. Wishing you a seamless and rewarding learning experience. Thank you so much for choosing these resources!

Lees meer Lees minder
4.9

2491 beoordelingen

5
2391
4
29
3
35
2
13
1
23

Recent door jou bekeken

Waarom studenten kiezen voor Stuvia

Gemaakt door medestudenten, geverifieerd door reviews

Kwaliteit die je kunt vertrouwen: geschreven door studenten die slaagden en beoordeeld door anderen die dit document gebruikten.

Niet tevreden? Kies een ander document

Geen zorgen! Je kunt voor hetzelfde geld direct een ander document kiezen dat beter past bij wat je zoekt.

Betaal zoals je wilt, start meteen met leren

Geen abonnement, geen verplichtingen. Betaal zoals je gewend bent via iDeal of creditcard en download je PDF-document meteen.

Student with book image

“Gekocht, gedownload en geslaagd. Zo makkelijk kan het dus zijn.”

Alisha Student

Veelgestelde vragen