BMGT 422-800 Project Management Exam 1 Questions
with Detailed Verified Answers (100% Correct Answers)
/Already Graded A+
Once a negotiation process begins, during its earliest phase we should
include the other party in a problem-solving session to identify alternative
outcomes. This technique is called:
Ans: Inclusive brainstorming
Creating action plans to address the needs of various stakeholder groups is
part of the _____ step of Block's framework for stakeholder management
Ans: Develop solutions
Exampromax - Stuvia US
Approved By:
A product is introduced into a market, gains the acceptance of a fickle
public, and finally is supplanted by a new and improved offering. This
phenomenon is known as the:
Ans: Product life cycle
The least amount of float is found:
Ans: On the critical path
The department chair had allotted plenty of time for all department (and
project) members to prepare sections of their five-year program review.
Administration demanded no less than 50 pages be devoted to a thorough
and thoughtful review of activities and goals. What happened to the report
was anybody's guess; no one had actually seen one or ever heard back from
administration once they had submitted it. Most of the project team
members thought the report was immediately sent to the steam tunnels
running underneath the campus or perhaps it would sit collecting dust as
part of a make-work program to justify an assistant VP's job. No wonder
that team meetings were poorly attended and that all the sections of the
report were filled with trite phrases and wide margins. This team suffers
from:
, 2 promax - Stuvia US 2025/2026
Ans: Lack of motivation
What is the late start time for Activity E given the activity times and
precedence requirements shown in the table?
Ans: 15
Gersick's model for team development rejects the standard model in favor
of something called:
Ans: Punctuated equilibrium
Stacey noted that the client was a cantankerous old man and that her
current project team lacked the requisite skills to work with him. Time was
Exampromax - Stuvia US
running short, so the BEST approach to making sure the project team had
Approved By:
the necessary skills was to:
Ans: Hire a contractor for the life of the project
Consider the Gantt chart shown below where the time scale is in minutes
and all activities are performed on an early start basis. How much slack is
available in the Great Hair Washing project?
Ans: 10 minutes
The expected cost of an item that is estimated at $5,000 with a task
contingency multiplier of 1.2 is:
Ans: $4,167
One purpose of a mission statement is to:
Ans: Explain the company's reason for existence
When their baby was ready to head off to college, the beleaguered parents
pulled out the college folder from their file cabinet and added up the cost of
putting their first child through college from 1995-2000. The mother