Revision Test 1
Question: What is the primary purpose of a project charter?
A. To assign tasks to team members
B. To formally authorize the project and define its objectives
C. To track daily progress
D. To close the project
Correct Answer: B
Rationale: The project charter formally authorizes the project and provides a high-level view of
objectives, scope, and stakeholders. It establishes the project’s existence.
Revision Test 2
Question: Which of the following best describes the Work Breakdown Structure (WBS)?
A. A hierarchical decomposition of the total project scope
B. A detailed list of project stakeholders
C. A schedule of project meetings
D. A risk management tool
Correct Answer: A
Rationale: The WBS breaks down the project into smaller, manageable components, making it
easier to plan, assign responsibilities, and control the scope.
Revision Test 3
Question: What is the critical path in project scheduling?
A. The sequence of tasks that determines the shortest project duration
B. The path with the highest budget allocation
C. The sequence of tasks that takes the least time
D. The tasks with the highest risk factors
Correct Answer: A
Rationale: The critical path is the longest sequence of activities that determines the minimum
project duration. Delays in this path directly affect the project finish date.
, Revision Test 4
Question: In project management, what does “scope creep” refer to?
A. A planned increase in project scope
B. Uncontrolled changes or continuous growth in a project’s scope
C. A reduction in project scope
D. The final phase of project closure
Correct Answer: B
Rationale: Scope creep is the uncontrolled expansion of project scope without adjustments to
time, cost, and resources, often leading to project overruns.
Revision Test 5
Question: Which process involves identifying, analyzing, and responding to project risks?
A. Risk monitoring
B. Risk management
C. Quality assurance
D. Procurement planning
Correct Answer: B
Rationale: Risk management encompasses the systematic process of identifying, assessing, and
mitigating risks throughout the project lifecycle.
Revision Test 6
Question: What is a stakeholder analysis used for?
A. To list out all the project deliverables
B. To identify and assess stakeholders’ interests and influences
C. To develop a communication plan only
D. To estimate project costs
Correct Answer: B
Rationale: Stakeholder analysis helps identify all parties involved, understand their
expectations, and gauge their potential impact on project success.
Revision Test 7
Question: Which of the following best describes a Gantt chart?
A. A bar chart that illustrates a project schedule
B. A network diagram of project tasks
C. A cost estimation tool
D. A risk management document