The Conditions of the Contract include b) General Conditions and
Supplementary Conditions.
a) Contract Forms, General Conditions, and Supplementary
Conditions.
b) General Conditions and Supplementary Conditions.
c) General Conditions, Supplementary Conditions, and Division
01.
d) Documents within the project manual, except the Bidding
Requirements.
The document recommended to organize preliminary construction b) Uniformat
information into a standard order on the basis of systems and
assemblies is:
a) MasterFormat
b) Uniformat
c) Outline Specifications
d) Project Manual
What activities take place in the Project Conception Stage? c) Feasibility studies and budget is set.
a) The engineers develop the mechanical and electrical
systems.
b) The site is selected and the demolition is done.
c) Feasibility studies and budget is set.
d) The program is evaluated and the engineers are selected.
1/27
,3/10/25, 9:36 PM CDT practice exam
All design and construction c) Scaled and nonscaled.
drawings can be classified as
one of two types of views:
a) Numeric and graphic.
b) Vertical and horizontal.
c) Scaled and nonscaled.
Exterior and interior
d)
Substitution requirements and c) Are stated in the Instructions to Bidders.
procedures during bidding
a) Are not allowed under
most public bidding
statutes.
b) Are modified by the
Supplementary
Conditions.
c) Are stated in the Instructions to
Bidders.
d) Are provided by requests by
telephone.
Submittal requirements for c) Division 01
Mechanical and Electrical work
are specified in:
a) General Conditions
b) Supplementary Conditions
c) Division 01
d) Division 22 and 26
The Procurement Requirements a) a part of the Procurement Documents, but not the Contract
are Documents.
a) a part of the Procurement
Documents, but not the
Contract Documents.
b) a part of the Contract
Documents.
c) a part of the Procurement
Documents but not the
Project Manual.
d) in the same part as the
Contract Modifications.
2/27
, 3/10/25, 9:36 PM CDT practice exam
Since he or she is most familiar c) Supply accurate information to the A/E
with a
product, the manufacturer's
representative should:
a) Write the specification section.
b) Review the specification
section.
c) Supply accurate information to
the A/E
d) Not be consulted in order
to avoid a conflict of
interest.
Which of the following requires b) Modification of the Work.
a Change Order?
a) Extension of bid date.
b) Modification of the Work.
c) Revision of Bidding
Documents affecting
construction cost.
d) Revision of Bidding
Documents affecting
completion time.