PK0-004 Project+ BEST STUDY GUIDE 2021/2022A milestone task on the critical path has been completed. which of the following should the project manager notify? A owner of predecessor task B project team C project sponsor D project steering committee correct answer- C During a project assessment, a project manager determines the initial project cost estimates were incorrect oh, and there is not enough budget left, including reserves, to complete the project. Which of the following actions should the project manager take? A alert the project sponsor of the situation B contact the customer and request more funding C announce the project will end due to lack of funds D attempt to save money in downstream activities correct answer- A Which of the following is the primary purpose of an MOA or an mou? A State expectations of all signatory parties to reduce potential misunderstandings B facilitate potential legal action and resulting remediation if one of the signatory parties violate any terms C enumerate a detail code of conduct for all employees, contractors, and subcontractors participating in the program. D provide transparency to competitors regarding all signatory parties correct answer- A two team members have concluded that documentation is not required due to the size of the current project. The project manager has encouraged them to align strictly with the process. which of the following conflict resolution techniques has the project manager utilized? A smoothing B forcing C compromising D avoiding correct answer- B The client accepts the critical design review. which of the following meetings should be held to move to the next step in the project? A execution B kickoff C closure D planning correct answer- B A project manager is working on the project charter. Which of the following phases does this describe? A initiation B planning C execution D closing correct answer- A A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do next? A update the project management plan B issue a change request C revise the project charter D evaluate the impact to the baseline correct answer- D Several team members report that meeting objectives are not being met. which of the following documents would a project manager free to make team meetings more effective? Choose two 1 create an s o w prior to each meeting and adhere to it 2 create a meeting agenda prior to each meeting and adhere to it 3 create a lessons learned list prior to each meeting and adhere to it 4 create a project charter prior to each meeting and adhere to it 5 create an action item list during the meeting and adhere to it 6 create a corrective action plan prior to each meeting and adhere to it 7 create a WBS prior to each meeting and adhere to it A 2,5 B 1,4 correct answer- A Which of the following documents should be used prior to high-level recording to key stakeholders? A dashboard B communication plan C statement of work D project charter correct answer- A A new project charter is being drafted. which of the following would be the best source for the high-level project requirements? A sponsor B project manager C project management office D project team correct answer- A Which of the following project document should be used to record the occurrence of an unplanned event? A action log B risk log C change log D issue log correct answer- D

Montrer plus Lire moins
Établissement
Cours











Oups ! Impossible de charger votre document. Réessayez ou contactez le support.

École, étude et sujet

Cours

Infos sur le Document

Publié le
11 mai 2022
Nombre de pages
159
Écrit en
2021/2022
Type
Examen
Contient
Questions et réponses

Sujets

Aperçu du contenu

PK0-004 Project+ BEST STUDY GUIDE
2021/2022


A milestone task on the critical path has been completed.

which of the following should the project manager notify?

A owner of predecessor task
B project team
C project sponsor
D project steering committee correct answer- C

During a project assessment, a project manager
determines the initial project cost estimates were
incorrect oh, and there is not enough budget left,
including reserves, to complete the project.

Which of the following actions should the project
manager take?

A alert the project sponsor of the situation
B contact the customer and request more funding
C announce the project will end due to lack of funds
D attempt to save money in downstream activities
correct answer- A

Which of the following is the primary purpose of an MOA
or an mou?

A State expectations of all signatory parties to reduce
potential misunderstandings

,B facilitate potential legal action and resulting
remediation if one of the signatory parties violate any
terms

C enumerate a detail code of conduct for all employees,
contractors, and subcontractors participating in the
program.

D provide transparency to competitors regarding all
signatory parties correct answer- A

two team members have concluded that documentation
is not required due to the size of the current project. The
project manager has encouraged them to align strictly
with the process.

which of the following conflict resolution techniques has
the project manager utilized?

A smoothing
B forcing
C compromising
D avoiding correct answer- B

The client accepts the critical design review.

which of the following meetings should be held to move
to the next step in the project?

A execution
B kickoff
C closure
D planning correct answer- B

,A project manager is working on the project charter.

Which of the following phases does this describe?

A initiation
B planning
C execution
D closing correct answer- A

A project in the execution phase is over budget, and tasks
on the critical path are on schedule.

Which of the following should the project manager do
next?

A update the project management plan
B issue a change request
C revise the project charter
D evaluate the impact to the baseline correct answer- D

Several team members report that meeting objectives
are not being met.

which of the following documents would a project
manager free to make team meetings more effective?
Choose two

1 create an s o w prior to each meeting and adhere to it
2 create a meeting agenda prior to each meeting and
adhere to it
3 create a lessons learned list prior to each meeting and
adhere to it

, 4 create a project charter prior to each meeting and
adhere to it
5 create an action item list during the meeting and
adhere to it
6 create a corrective action plan prior to each meeting
and adhere to it
7 create a WBS prior to each meeting and adhere to it

A 2,5
B 1,4 correct answer- A

Which of the following documents should be used prior to
high-level recording to key stakeholders?

A dashboard
B communication plan
C statement of work
D project charter correct answer- A

A new project charter is being drafted.

which of the following would be the best source for the
high-level project requirements?

A sponsor
B project manager
C project management office
D project team correct answer- A

Which of the following project document should be used
to record the occurrence of an unplanned event?

A action log
B risk log
$13.99
Accéder à l'intégralité du document:

Garantie de satisfaction à 100%
Disponible immédiatement après paiement
En ligne et en PDF
Tu n'es attaché à rien

Faites connaissance avec le vendeur

Seller avatar
Les scores de réputation sont basés sur le nombre de documents qu'un vendeur a vendus contre paiement ainsi que sur les avis qu'il a reçu pour ces documents. Il y a trois niveaux: Bronze, Argent et Or. Plus la réputation est bonne, plus vous pouvez faire confiance sur la qualité du travail des vendeurs.
mikaelso Chamberlain College Of Nursng
S'abonner Vous devez être connecté afin de suivre les étudiants ou les cours
Vendu
65
Membre depuis
4 année
Nombre de followers
62
Documents
281
Dernière vente
6 mois de cela
SURE EXAMS

I know how frustrating it can get with all those assignments mate. Nursing Being my main profession line, i have essential guides that are A graded, I am a very friendly person so don

3.8

11 revues

5
3
4
6
3
0
2
1
1
1

Récemment consulté par vous

Pourquoi les étudiants choisissent Stuvia

Créé par d'autres étudiants, vérifié par les avis

Une qualité sur laquelle compter : rédigé par des étudiants qui ont réussi et évalué par d'autres qui ont utilisé ce document.

Le document ne convient pas ? Choisis un autre document

Aucun souci ! Tu peux sélectionner directement un autre document qui correspond mieux à ce que tu cherches.

Paye comme tu veux, apprends aussitôt

Aucun abonnement, aucun engagement. Paye selon tes habitudes par carte de crédit et télécharge ton document PDF instantanément.

Student with book image

“Acheté, téléchargé et réussi. C'est aussi simple que ça.”

Alisha Student

Foire aux questions