Which of the following should a special inspector contact
the contractor about immediately?
A) If the concrete temperature is 80 degrees
B) If the slump calls for a maximum of 4' but is 6'
C) If the air content calls for 6% but is 3%
D) If the steel isn't tied properly - ANSWERS-B and C
Can a material not listed in the IBC be used for
construction?
A) Yes
B) No - ANSWERS-A
, Who should NOT hire the special inspector?
A) The building official
B) The contractor
C) The Owner
D) The RDP - ANSWERS-B
Who's job is it to ensure that the special inspector has an
approved set of plans?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - ANSWERS-B
Who should the special inspector notify upon arrival to the
jobsite?
A) The building offficial
B) The contractor
C) The owner
D) The RDP - ANSWERS-B